Effectivity answers the most practical question in engineering change: which orders get the new version? Without it, every change would apply to everything at once, including the 300 orders already being built.
Kinds of effectivity
| Type | Applies from | Common use |
|---|---|---|
| Date | An order or build date | Configure-to-order products, price and option changes |
| Serial | A unit serial number | Machinery, vehicles, anything serviced by serial |
| Lot | A production batch | Process and material changes |
Choosing the date
The right cut-in date is a negotiation between engineering (as soon as possible), purchasing (when the old stock runs out), the plant (not in the middle of a big run) and sales (not the week before a major project ships). Picking it well is half the change.
Effectivity in a configurator
In a configurator, effectivity usually lives on BOM lines and rules. The same configuration ordered on 30 November and on 1 December can legitimately produce different BOMs. The Rules Lab shows this: the return lever switches from rev A to rev B on 1 December 2026, and a finish becomes unorderable on 1 January 2027, without anyone editing an order.
Questions people ask
What happens to orders placed before the cut-in?
They keep the old version, unless the change is urgent enough (a safety issue, for example) to justify reworking them.
Can effectivity be used to retire options?
Yes. An end date on an option is the cleanest way to phase it out while protecting open quotes.